Project development is the early phase where a project is made ready for an investment decision: requirements, concept, budget, schedule and risks in place.

The development phase is where expensive mistakes are either caught or built in. I have spent most of my career here – turning a business idea into a technical concept, a realistic budget and a plan that management, board and suppliers can all work from.

The work typically covers

  • Requirements specification, aligned with users, operations and management
  • Concept selection and layout with a focus on how the plant works for the operator
  • Feasibility, cost estimates and business case
  • Master schedule and phasing (stage gates)
  • Energy and utility studies, e.g. grid connection versus island operation
  • Risk register and project risk assessment – what can go wrong, and what we do then

What you get

  • Decision basis for management or the board
  • Concept description and layout
  • Budget with stated uncertainty, and a schedule
  • A clear plan for the next phase – tender or detailed design

Examples

Land-based aquaculture · 2019–2025

AquaCon

Over USD 100 million

Engineering manager · Oslo / Maryland, USA

Greenfield facility for 12,000 tonnes of salmon a year – production concept and technical solution from idea phase to tender and basic design, including permits.

  • Production plans that formed the basis for sizing each production unit
  • Modular RAS design: instead of a new system for each life stage, one standard module large enough for economies of scale – biomass and feeding capacity was met by building the right number of modules
  • The gains of repetition: the same pumps and components in every module, faster construction because the same system is installed again and again, and a smaller spare-parts stock
  • Detailed tender documents and selection of technology suppliers
  • Link between US engineering and a European process supplier
  • Power supply and load profiles: grid connection vs. island operation on gas, biomass, solar and waste heat
  • Energy and mass balances, cooling demand and coordination of biogas and wastewater plants
  • Dialogue with US authorities on the discharge permit and participation in board meetings

Land-based aquaculture · 2024–2025

Atlantic Sapphire

Design review consultant · Florida, USA

Independent design review of one of the world's largest land-based salmon farms, with the findings presented to the board.

  • Identified critical bottlenecks affecting operation and capacity
  • Documented under-sizing and prepared turnaround proposals with prioritised actions
  • Report with concrete optimisations and quick wins for reliability and production

Process and water treatment · 2025–2026

Novonesis

30+ tie-ins in a live plant

Tie-in manager · Kalundborg, Denmark / Poland

Responsible for 30+ tie-ins between the existing plant and new systems, carried out during operation with minimal disruption – as part of a wastewater treatment expansion worth more than DKK 2 billion.

  • Planned local plant shutdowns with a focus on safety, in close cooperation with operations
  • Managed 5 contractors and suppliers across piping, electrical and automation
  • Coordinated detailed design and fabrication of pipe components at Eurosteel in Poland
  • Walkdowns, P&ID reviews and quality assurance of critical installations
  • Turned the basic design into a prioritised plan with a visual overview